OREANDA-NEWS. The first ore from Zapolyarny open-pit mine of Verkhne-Munskoe kimberlite field in the Republic of Sakha (Yakutia) was delivered to the stockpile of the processing plant No. 12 at Udachny Mining and Processing Division. There are plans to remove a total of 75,000 tons of ore from the new deposit before the end of the year.

All the transported ore will be processed at the processing plant No. 12. Experts will confirm the diamond content in ore and develop the processing technology. It is necessary for the start of the commercial operation of the deposit that is scheduled for 2018.

On October 2, Scania road train had its first test run to confirm that the equipment and the road are ready for the removal of ore. Since October 4, four road trains have started regular trips: one Scania road train and three Volvo road trains, all with the load capacity of 95 tons. The road train covers the distance from the motor depot of Udachny Mining and Processing Division to Zapolyarny open-pit mine in 5-6 hours non-stop on the average, the return trip takes the same time.

Finishing and furnishing works for the service lane from Udachny Mining and Processing Division to the deposit are underway: temporary road signs are being installed, the roadbed forming the upper structure of the road is being filled, ice-melting materials are being brought.

The development of Verkhne-Munskoe deposit is ALROSA’s largest investment project. The deposit is located 170 kilometers from Udachny Mining and Processing Division.