OREANDA-NEWS. On 07 May 2008 was announced, that since the beginning of the current year, Lipetsk powermen have been actively repairing networks. The sum of RUR 5.9 mn has been already assigned for repairs of own networks. And the repairs of ownerless networks will cost RUR 9.9 mn. Thus, the major attention is paid to complex overhaul of the equipment.

In order to provide uninterrupted electricity supply of consumers of the area, clearing of OL 6-10-35-110 kV routes is performed. From January to March 2008, clearing of 10 hectares is executed.

In the 1st quarter the target for repairs of transformer substations of TS 6-20/0.4 kV was executed by 149 %. Instead of planned 45 TS, the amount of 67 TS was repaired. Distributive networks of 108.2 km of 0.4-20 kV were repaired that cost RUR 2.6 mn.

According to Deputy Chief Engineer for Operation and Repairs Sergey Vasilev, work on repairs of buildings and constructions is held; the sum of 500 thousand rubles was spent by Lipetskenergo branch of IDGC of Centre for this purpose.