OREANDA-NEWS. Branch of JSC “MOESK” – The Southern Electric Grids have summed up the fulfillment totals of the investment program in 2012. The capital investments into the investment projects have amounted to RUR 4,018 mln, which exceeded the planned indicator by 103 %.

4,394 energy facilities were included into the investment program. 35-110 kV substations (SS) “Krasnogorka”, “Aparenki”, “Yubileynaya”, “Bylovo”, “Bor” became the investment program’s top-priority facilities in the South of Moscow region. Over 600 MVA production capacities have been introduced for the year.

Works on connection to the electric grids of a socially significant facility – new micro district “Kuznechiki” have been completed in Podolsk region, where new SS 110 kV “Fetischevo” was commissioned in December.

Much attention was paid to the works at the facilities of 0,4/6/10 kV distribution grids. 805 km lines with the voltage of 0,4/6/10/110 kV were reconstructed. The capital investments’ amount for the given direction implementation was RUR 1,538 mln. The biggest volume of the works in this direction was made in Chekhov, Ramensky, Domodedovo regions.

In 2013 year, which has come, the branch’s investment activities will be aimed, as before, at re-equipping and reconstructing of the equipment, at constructing of new energy facilities. The given arrangements will make it possible to provide a continuous function of the energy grid complex, good quality and reliable power supply of the consumers of Moscow region’s South.