OREANDA-NEWS. The crushing cylinder of the mill MSCHC 2,7x3,6 for "Svyatogor" Works passed the RZhD committee check and was shipped to the Customer's Krasnouralsk site. 52-ton component was shipped ahead of schedule.
 
The rest of mill components whose total weight is 140 tons will be shipped to the Customer on six vehicles as soon as they are ready. Two of them will be shipped within the next few days.
One more mill MSCHC 2,1x3,0 will be ready for shipment next week.
UMMC and "Uralmashplant" signed the contract in October 2013. 19 mills of various sizes should be manufactured on a tight timetable, including those exceeding 7,0 m in dia. that are untraditional for the plant. The Engineering Direction formed a new mill department specially for this work.
The erection of the equipment will be carried out under the supervision of "Uralmashplant" engineers. On April 15, plant specialist will leave for "Svyatogor" to hold consultations with the erection entity.

UMMC and its management expressed confidence owing to the large-scale program of production facilities upgrade and purchase of new modern machine tools implemented during the last five years with the support of the strategic financial partner - Gazpormbank.
The joint-stock company "Uralmashplant" is one of the leaders on the Russian market of equipment for metallurgy, mining industry, oil and gas industry, building material industry and power engineering industry. The strategy of the company's development aims at creation of a world-class machine-building company, capable to completely fulfill all equipment requirements a customer may have.
With support of the principal shareholder - Gazprombank - Uralmashplant has developed and is implementing an investment program providing for fundamental modernization of metallurgical, forging, welding, assembling and other production facilities.