OREANDA-NEWS. VNIIR Hydroelectric Automation continues reconditioning of Process Control Systems at Kamskaya HPP, RusHydro's subsidiary. Much work was fulfilled during 3rd quarter 2014 under our specialists' direct supervision:

Relay Protection and Automation systems were constructed, installed and launched in OL-220 kV Vladimirskaya-1, OL-220 kV Soboli, OL-110 kV TPP-13-1. All overhead lines were successfully launched after 72 hours testing of complete installation;

New equipment of 2nd differential protection for 110 and 220 kV bus bar was delivered;

Final batch of equipment was shipped for installation of auxiliary Process Automation System;

Process Control Systems for substation's drainage and submerged pumps were installed;

Upper level of data acquisition and processing system was commissioned.

Due to coordinated teamwork VNIIR Hydroelectric Automation completely fulfilled quarter program of equipment reconstruction and reconditioning at Kamskaya HPP within tight outage schedule.