OREANDA-NEWS. IDGC of Centre - Tambovenergo division summed up the work on grid connections for 2016. During the reporting period, the enterprise connected to power grids 1,360 facilities with a total capacity of 55.9 MW, which is 65% higher than the corresponding figures of the previous year (33.76 MW).

The large facilities, which Tambovenergo connected to the grid in the past year, included significant for the Tambov region construction companies and agro-industrial complexes: LLC "TambovCapitalProject", LLC "Spetsmontazh", LLC "New Town", LLC "Capital" (all - residential houses), LLC "Tambov Turkey" and LLC "Tokarevskaya Poultry Plant", LLC "Agrocombinat Tambovkrakhmal" (a factory for production of modified starch), JSC "Izberdeevsky Elevator". 128 contracts for grid connection of significant facilities of communal infrastructure in the region were also performed (street lighting and outdoor lighting of motor roads).

In carrying out its obligations in a timely manner and in full on connection to the grids of large industrial, residential and social facilities, small and medium-sized businesses, Tambovenergo promotes the expansion of the tax base in the region, creation of new jobs and implementation of effective housing policies, thereby supporting the socio-economic development of the Tambov region.