OREANDA-NEWS. Statoil has, on behalf of the license partners, decided to exercise the option for engineering, procurement, construction and installation (EPCI) of a gas module that will increase gas processing capacity on the Troll B platform.

The contract has a value of approximately NOK 370 million, and is an option in a front-end engineering and design (FEED) contract awarded to Aker Solutions in January 2016.

“The gas module is an important contribution to reaching the licensees’ IOR ambition for the Troll field. It will raise production capacity on Troll B and help us recover as much as possible of remaining resources during tale end production. From the module starts up in the autumn of 2018 until Troll B is shut down in 2025 it will increase recovery by around 4.7 million barrels of oil,” says project director Eric Normann Ulland.