OREANDA-NEWS. October 12, 2009. The Garadagh Cement OJSC has started implementing   the building project of №6 new kiln on cement production by means of dry method.

Director General of the Garadagh Cement OJSC Khoria Adrian said that at present work on various phases is being proceeded within the frames of building of new kiln.

“Presently, engineering and architectural works, which are close to completion, are being carried out. At the same time, new buildings on production of clinker are already prepared. We intend to build 2-3 such buildings. All works, which are being conducted now, proceed under ground-level. As early as February, 2010, we will start overground work,”  K. Adrian said.

According to him, construction of new kiln will be finished  in the second quarter of 2011.

Financing targets the period of building from mid-2009 to the first half of 2011, when new kiln is expected to be put into operation.