OREANDA-NEWS. The Asian Development Bank (ADB) has approved a loan of $115 million and $3.8 million in grants  to help Sri Lanka meet its goal of achieving 100% electrification and improve the reliability of its electricity supply, including in former strife-torn areas and on small isolated islands.

The grants comprise $2 million from the Japan Fund for Poverty Reduction and $1.8 million from the Clean Energy Fund under the Clean Energy Financing Partnership Facility, a multi-donor facility administered by ADB.

Hybrid renewable energy systems using a combination of wind, solar and efficient diesel generation, along with the installation of energy-storing long life lithium-ion batteries will provide  a reliable electricity supply for communities on three isolated islands in the Jaffna area of the Northern Province (Analativu, Delft, and Nainativu). A renewable energy micro-grid will also be installed in Western Province.

To upgrade the existing medium voltage network, new lines and associated equipment will be installed, while the rural electrification network will be extended with thousands of kilometers of low voltage lines put in place to connect households to the national grid, and thousands of distribution meters with a remote reading facility installed. 

The project includes a micro-grid pilot scheme, financed by the Clean Energy Fund, which will demonstrate cost-effective management of power resources and reduce the burden on the national grid. It is the first time this concept is being trialed in Sri Lanka. The assistance from Japan will be used to help train rural community members on the safe use of electrical equipment and on potential livelihood opportunities arising from reliable power supplies.  Local community members will also be tapped to work in maintenance teams to carry out basic repairs and to operate and maintain the hybrid systems.

Improvements to the medium voltage network, meanwhile, will enhance the quality and reliability of electricity supplied to more than 493,000 customers, while the rural upgrades will help deliver reliable electricity to over 35,700 rural households.

The project will run for 5 years with an expected completion date in September 2021.