OREANDA-NEWS. Two arc suppression coils were put into operation and there was also made a transfer of auxiliary transformers at substation "Gorbunovo" 110/35/10 kW which provides power supply tone of the biggest dwelling microdistricts of Nizhni Tagil - Galjano-Gorbunovsk housing estate. These works were made by contracting organization "Energorekonstruktsia" under exploitation order by Sverdlovenergo 2007.

Specialists of Nizhnetagilsk power networks are awaited by one more challenging work: soon there should be started reconstuctionof open switchgear at substation "Krasnouralsk" 110/35/6 Kw. This substation provides power supply for such large consumers as JSC "Svjatogor" UGMK.