OREANDA-NEWS. In JSC “Sverdlovenergo” works are already finished on 2 objects out of 17 which were provided by the Agreement between region authorities and RAO “Unified Electric Power System of Russia”.

In Artemovsk power networks of JSC "Sverdlovenergo" works on reconstruction of 2 transformer substations 10 kW (Mironovo and Makhnevo villages) are made, as well as the reconstruction of power line 0,4-10 and TP-0,4/10 kW in Deevo, Alapaevsk district. Reconstruction of TP has helped to meet the growing requirement of citizens in electric power supply of high quality in these two localities. Reconstruction of networks in Deevo improved the reliability of its electric supply.

More than 4 mln rbl was invested in the works.