OREANDA-NEWS. July 11, 2007. Medium repair of oil circuit breaker was made in Nizhni Tagil at one of the oldest substations in the town - substations "Krasny Kamen" 110/35/6 kW which provides power supply for central part of Nizhni Tagil, reported the press-centre of JSC “Sverdlovenergo”.

Similar work was also made on substation "Drozhevaya" 110/6 kW which supplies with power Kirpichny village- such enterprises as brick-making and yeast plants and preventative clinic "Sosnovy bor".

Recently team of contractor - Electrical repair company - set to work at substation of Prigorodny district - substation "Uzhakovo" 35/10 kW. Constructors are going to make repair work on disconnecting switches 35 kW and change power line supports' covering in 2 weeks.

But this is not all what is planned to work out in summer period by Nizhnetagilsk power networks. Short-range plans include equipment repair at substation "Pikhtovaya" 110/6/6 kW which provides electricity for citizens of micro district Vagonki (about 100.000 citizens). After many years of making plans and waiting for their realization, reconstruction should be started at substation "Krasnouralsk" 110/35/6 kW this year. Thanks to this JSC "Svjatogor" UGMK will "breathe freely" at last.

Repair expenses for general production facilities of Nizhnetagilsk power networks are expected to be more than 56 mln rbl this year. And more than 25 mln rbl have been already mastered for the present day.