OREANDA-NEWS.The second pressure transformer with capacity 10 MW was installed at substation "Martush"  in Kamensk-Uralskiy, the press service of Sverdlovenergo Public Company reported. Works for reconstruction of "Martush" substation are maintained, according to the investment program, by JSC Sverdlovenergo and were started in June 2007. More than 52 mn rubles out of the total sum meant for investment program and equal to 72,5 mn rubles have been already applied. As of the present moment,  installation work of open switch gear 110 kW and equipment of standard switch gear 10 kW is finished. There were also installed 2 modern electro-gas switching gears. Installation of new transformer will help satisfy the demand in power capacity and energy for cottage area in Martush village, recreation center in Brod village, silicate sand cast of CJSC "Simat", as well as residents of new district "Uzhny" in Kamensk-Uralskyi. Besides, there should be installed a 110 kW tie-breaker at the substation, which will provide a more reliable feed circuit in both work and repair regimes.