OREANDA-NEWS. December 18, 2007. Irkutskenergo will in full implement a plan of designing and construction of priority power facilities till the end of the year, the company's press service reported. 
 
Irkutskenergo Grid Company Ltd. (branch of Irkutskenergo) till the end of the year will in full implement a plan of designing and construction of priority power facilities within the limits of the agreement on social and economic cooperation between administration of the Irkutsk area and JSC Irkutskenergo, the press service of the enterprise reported.

In 2007, Irkutsk Grid Company performed reconstruction of the electric power supply pattern of the Irkutsk-Cheremkhovo region, continued construction of OL 35 kV Ulman Karam Kazachinsk of the Lensky region, completely constructed OL 35 kV Chernorud-Sarma in the Olkhonsk region.

Saltykovo-Chechuisk section was put into operation, as well as OL 35 kV Saltykovo-Petropavlovsk in the Kirensky region. Works on installation of supports for OL 35 kV Golumet-Novostroika in the Cheremhovo region are conducted. Designing of OL 35kV Novo-Zhilkino-Razdolie-Oktyabrskoe in the Usolsky region comes to an end.

There started construction of substation 110/35/10 kV in the Rubakhino settlement of the Nizhneudinsk region, designing of Sb 220/35/10 kV in Novaya Igirma area of the Nizhneilimsky region, research and designing of substations Pribrezhnaya 110/35/10 kV in Angarsk, Berezovaya 110/10 kV in Molodezhny settlement of the Irkutsk area, Bystraya 110/10 kV in Slyudyansky region. Substation 110/10 kV was put into operation in Ust-Orda settlement.

Designing and construction of OL 6kV and regional substation for improvement of electric power supply of the central part of Tulun has been finished; construction of electric power supply facilities of Novoirkutsky microdistrict is being finished, facilities of the Homutovo-Granovshchina district of the Irkutsk area were put into operation. In Irkutsk the external electric power supply of children's clinical hospital was improved, the cable line of 6kV for the electronic transmission center was laid.

According to Irkutskenergo press service, as of 5.12.2007 the sum of 475.2 million rubles was invested from the sum of 500 million rubles planned to be invested in 2007. The rest of the sum will be invested till the end of the year.