OREANDA-NEWS. March 25, 2008. First industrial coal from the well "Butovskaya" is being planned to win in October or November 2010. On the well "Butovskaya" road heading jobs have already started in two breasts – on pipeline and itinerary drifts. The first meters to the plateau Artelnii, to which there are more than 300 meters of silt and ledge rocks, are passed. Form the beginning of the digging the preparatory stage of building of the well may be finished. Among ground constructions for work are prepared the following: an approach road, a mains, a boiler house, an engineering shop, a store house for materials; the building of an electric substation intended for 35 kilovolt is on the finishing stage.