OREANDA-NEWS. On 22 December 2008 was announced, that a Board meeting of “OGK-2” was held on November 28, 2008, the following decisions were adopted:

1. Determine as priority directions: the investment project “Construction of 2 power units 330-400МW at Serovskaya GRES” and the investment project “Construction of 2 power units 660МW at Troitskaya GRES”.

2. Determine the commissioning terms of new power units:

2.1. The investment project “Construction of 2 power units 330-400МW at Serovskaya GRES” (combined-cycle power unit №9 – November, 2012; combined-cycle power unit №10 – November, 2013)

2.2. The investment project “Construction 2 power units 660МW at Troitskaya GRES” (power unit №10 - November, 2013; power unit №11 - November, 2014).