OREANDA-NEWS. July 6, 2009. KAMAZ production units completed vehicle assembly and parts kitting for June orders.

1606 kits were assembled at Automobile Plant. Certain KAMAZ finishing production units engaged in production delivery and shipment fulfilled the June plan – 1719 kits of vehicles and spare parts to the tune of 320.5 million roubles.

On 23 and 24 June some of the company’s blank productions – iron and steel casting units of OAO KAMAZ-Metallurgy ¬– worked to create buffers of work for July.

KAMAZ-Diesel closed an assembly plan having produced 1520 engines. It’s planned to deliver 1779 engines and power units in all to the KAMAZ mother gathering conveyor and customers during the month.

Production was launched on 1 July. The units of OAO KAMAZ-Metallurgy were the first to start working. Then machine process and assembly productions and finally the mother gathering conveyors of Automobile Plant will join in with the work.