OREANDA-NEWS. October 29, 2009. JSC "ZTR" has signed two contracts with Crimea ES NEC “Ukrenergo” for supply of transformers for s/s "Sevastopol".

АТDTN-125/220 MVA transformer will be installed at substation within the bounds of modernization project for the purpose of improvement of power supply safety for Sevastopol city and consumers of Crimea south coast.

АТDTN-200/330 MVA transformer is to be installed based on the project of overhead line "Simferopol-Sevastopol" conversion to 330 kV that should ensure an output increase of one of the main substations of the Crimean peninsula.

The transformers are scheduled to be shipped in October and November of 2009, respectively.