OREANDA-NEWS. March 16, 2010. In the branch of IDGC of Centre, JSC – “Voronezhenergo” there was held the meeting devoted to discussion of technical issues regarding technological connection of the Heat electric generation plant-2 which is being constructed to Voronezhenergo grids.

Employees of IDGC of Centre, JSC, the branch of “TGC-4”, JSC — “Voronezh regional generation”, Voronezh regional dispatching department (RDD) coordinated their actions for trial startup of the installation.

Representatives of TGC-4 which deals with construction of the Heat electric generation plant-2 confirmed readiness of scheme performance for trial startups. IDGC of Centre defined terms and volumes of works necessary for technological connection. For the new up-to-date installation to be connected within the shortest terms, it is required to reconstruct power grid equipment and perform a number of construction works.

The decision on development of general scheme of trial startups between Voronezhenergo, TGC-4 and Voronezh RDD with approval of week-to-week schedule of work performance by all parties was taken at the meeting. These works are carried out upon agreement with general contractor for design of power grid construction items of this connection — “Voronezhenergo”, JSC.

Dmitry Rybnikov, Head of the Department for Technical Development of IDGC of Centre, JSC, noted: “Power delivery to the Heat electric generation plant-2 will have positive impact on economy of the region, eliminate power deficit, extend possibility of connection of new consumers. For we to deliver successfully power to such large item as the Heat electric generation plant-2, we need the corresponding infrastructure. This task will be solved in the nearest future”.

It is planned that the Heat electric generation plant-2 will have been put into operation before October 1, 2010.