OREANDA-NEWS. November 11, 2010. "Zaporozhtransformator" (ZTR) delivered 2 autotransformers to Republic of Belarus. The delivery was related to the project as for reconstruction of substation "Miradino" in Mogilevsk region.

Contract with the Company "Belelectroinvest" Ltd. as for delivery of two autotransformers rated for 125 MVA 110kV was signed in March, 2010. At present autotransformers have been delivered to S/S Miradino.

Erection with assistance of JSC "ZTR" supervisor-engineer is scheduled for October. Commissioning of autotransformers is expected to take place in December, 2010.

Within cooperation period with Belarus, JSC "Zaporozhtransformator" has delivered to Republic 192 units of equipment in total, including 8 units in the year 2010.      

Substation "Miradino" that has been put into operation in the year 1959 is one of the most powerful and main substations rated for voltage 330-220-110-35kV in power supply system of Republic of Belarus. Technical equipment of S/S Miradino is in a process of complete renewal due to high level of moral and physical wear.