OREANDA-NEWS. November 12, 2010. By the reconstructed lines of high voltage - 110 kW of IDGC of North-West's branch "Vologdaenergo", the transmission of the electric power produced by CHP “Krasavino” to the power transmission lines -110 kW will be provided.

IDGC of North-West's branch "Vologdaenergo" has started the reconstruction of the 110 kV overhead line at “Krasavino” substation. The substation is situated in Velikiy Ystyug’s district (Vologodskaya  region). Capital investments into implementation of the investment project will exceed around RUR 35 million.

During the reconstruction, the contractor “Peterburgenergostroy” will install 29 metal bearing constructions and 4, 7 km of wire for the lines of high voltage -110 kW. At the present time the contractor  transfers equipment and personnel to the place of operations.

The project is implemented in the frames of the contract between IDGC of North-West's branch "Vologdaenergo"  and Regional energy commission of  Vologodskaya region.  According to the contract, the objects of generation, which were constructed in the course of the “Programm of guarantee of reliability and developing of energy sector of  Vologodskaya region for the period 2007-2012” are included to the investment program.

CHP “Krasavino” is one of the top-priority objects. CHP “Krasavino” was constructed in 2009 on the Government of  Vologodskaya region and Check Republic initiative. By the reconstructed lines of  high voltage -110 kW of IDGC of North-West's branch "Vologdaenergo", the transmission of the electric power produced by CHP “Krasavino” to the power transmission lines -110 kW will be provided.

Realization of the project will increase the transmission capacity and improve the reliability of the power transmission lines 110 kW from substation 110/35/6 “Velikiy Ystyug” to substation 220/110/10 “Zaovrag’e”. By this power transmission lines the electric power comes from CHP to the energy system. Also, the realization of the project will give the possibility for development of infrastructure of  Velikiy Ystyug’s district  and Vologda region.

The implementation of the fixed assets is planned for the second half of the year 2011.