OREANDA-NEWS. February 17, 2011. JSC “Yenisei TGC (TGC-13)” and CJSC “Ural Turbine Works” have concluded a contract for supply of a 120 MW steam turbine of type T-120/136-12,8-8MO to Abakan CHP.

Under the contract “Ural Turbine Works” undertake to deliver the turbine late in Q2 2012.

Note: in the current year “Yenisei TGC” has launched an investment project for construction of a new unit at Abakan CHP. The project is aimed at increasing the installed capacity of the plant by 120 MW. The steam turbine is to be integrated into the new 500 t/h boiler. Under the Contract for Supply of Power, launch of the new Abakan CHP unit is scheduled for October 2013.

Currently, the installed electrical capacity of Abakan CHP is 270 MW. The plant installed thermal capacity is 625 Gcal/h. It already utilizes steam turbines fabricated by the Ural plant which are T-110/120-130-4 st. No. 2 and T-110/120-130-5 st. No. 3 commissioned in 1984 and 1989 accordingly.