OREANDA-NEWS. May 13, 2011. For I quarter of 2011, “IDGC North-West” received 4382 requests for technical connection with a total capacity of 355 MW.

For the 1 quarter of 2011, JSC "IDGC North-West” executed the 1665 contracts for technological connection with total capacity of 29,6 MW, including 1561 contracts for technological connection of power plants up to 15 kW with a total capacity of 14.1 MW. During the same period in 2010, “IDGC North-West”  performed 1076 contracts with total capacity of 21.6 MW, including 955 contracts for technological connection of power plants up to 15 kW with a total capacity of 7.2 MW.

For I quarter of 2011, “IDGC North-West” received 4382 requests for technical connection with a total capacity of 355 MW. Number of requests compared with the same period in 2010 increased by 979 units. And the capacity increased by 116 MW.

In comparison with the same period in 2009, the number of requests for technological connection of power plants with capacity up to 15 kW in I quarter of 2011 increased by 2522 units. (173%), and the requested capacity increased for 31.8 MW (318%).