Ilim Allocated over RUR 310mln to Increase Power Generation Capacity
OREANDA-NEWS. July 12, 2011. Ilim Group is completing the second stage of the Rebuild of Facilities for Preparation, Storage, and Feeding Wood and Bark Waste for Incineration project launched last year. The total cost of the work under the project exceeds RUR 310 million.
The key purpose of the project is to increase the Mill's power generation capacity through incineration of bark waste in bark boilers which will yield additional steam and electric power at the Mill. This will facilitate the reduction of third-party energy consumption.
Bark waste supply was planned using a state-of-the-art conveyor system.
Project completion in late 2011 will facilitate annual power savings of up to RUR 50 million to significantly reduce finished product cost.