OREANDA-NEWS. November 08, 2011. In 2011, the Ukrzaliznytsya (the State Administration of Railway Transport) invested 5.3 billion UAH to execute the State target program of preparation and holding in Ukraine of a final part of the European Championship of 2012 on football.

The preparatory work for the railway infrastructure is carried out in many areas. In areas of implementation speed train Lviv – Zdolbuniv, Zdolbuniv - Shepetivka - Korosten - Kyiv, Kyiv - Poltava - Kyiv, Poltava - Krasnograd – Lozova, Lozova – Donetsk, there have been performed following repair of the track: modernization and overhaul of equipment automation, telemechanics and communication, electricity equipment modernization and construction works.
There is led electrification of the introduction of high-speed train Poltava - Krasnograd - Lozova and construction of traction substation Sagaydak of the Southern Railway.

For unloading areas, which will run passenger trains, there is conducted a comprehensive modernization of the railway in Poltava - Burty - Korystivka.

Also, it is continued construction of the railway - motor bridge across Dnieper in Kyiv. The traffic interchange of "Vydubychi" is under construction now, namely: it is fulfilled construction and installation of towers spans the railway overpass, railway and road tunnels and track to ensure direct communication Darnytsya - Trypillya.