OREANDA-NEWS. April 10, 2012.  The recorded sum total of CAPEX on technological connection implementation during the period referred to is 1,979.4 bln RUR which makes 38.3% of the total volume of the Investment Program.

IDGC of the North-West, JSC proceeds from technological connection in 2011 made 883.8 mln RUR.

The recorded sum total of CAPEX on technological connection implementation during the period referred to is 1,979.4 bln RUR which makes 38.3% of the total volume of the Investment Program.

The main sources of IDGC of the North-West technological connection CAPEX funding were the electric energy transmission tariff (1,231 mln RUR) and technological connection fee (748.3 mln RUR).

Shortfall in IDGC of the North-West income from technological connection of applicants up to 15 kW having made in 2011 1,047.2 mln RUR

On the whole, according to the data at the disposal of the Department for Prospective Development and Technological Connection of IDGC of the North-West, during the previous year the company executed 12,745 contracts for technological connection.

The total volume as per the applications supplied, contracts concluded and executed in 2011 increased almost twofold as compared to 2009.