OREANDA-NEWS. July 20, 2012. According to the results of open bidding queries, JSC "Gazprom" announced LLC "STROYGAZMONTAZH" the winner of the tender on construction of facilities of I and II start-up complexes within "Reconstruction of Okhansk — Kirov Gas Pipeline Branch" Project.

Client — CJSC "Gazprom invest Yug".

"STROYGAZMONTAZH" will construct 84 km of new gas pipeline in parallel to the operating Okhansk — Kirov gas pipeline branch routed from trunk gas pipeline Perm — Gorky to Gas Distribution Station-1 in Kirov.

At present "STROYGAZMONTAZH" has started construction of linear part of the gas pipeline as part of I start-up complex at 48 — 91 km section: there a pipe welding station was installed; more than 30 units of construction equipment were delivered at site; and more than 100 people were mobilized. The new gas pipeline will be routed across the Perm Territory and the Republic of Udmurtia.