OREANDA-NEWS. August 13, 2012. LLC “STROYGAZMONTAZH” was announced the winner of an open request for bids for construction of compressor station Kubanskaya as a part of “Capacity increasing of RussiaTurkey gas pipeline” on section “Izobilnoye – Dzhubga” to ensure gas supply to Dzhubga – Lazarevskoe – Sochi gas pipeline. The project is being implemented to meet the needs of JSC “Gazprom invest Yug”.

Construction of CS Kubanskaya will take place on the territory of the Ust-Labinsk district of the Krasnodar Territory. Four gas pumping units (3 working and 1 standby) with a total capacity of 48 MW are planned for installation at the compressor station.

At the moment, with a help of subsidiary company “SCC “Gazregion”, “STROYGAZMONTAZH” is relocating equipment, arranging a temporary residential camp, construction base and a site for storage of material and technical resources. In October, the builders will begin construction of the compressor plant. Commissioning of CS Kubanskaya is planned for November 2013.