OREANDA-NEWS. September 7, 2012. Mosmetrostroy completed construction of spans at Zamoskvoretskaya line site. Tonnel party № 6 of Mosmetrostroy successfully performed the drivage of a 650m long section for the right span. It was the last section to be driven at the site making a 3km long way between Krasnogvardeyskaya and Alma-Atinskaya stations.

TBM constructed the tunnel with the diameter of 6m from Proektiruemiy passage to turn-around station dead ends and within time schedules broke into the target shaft. Thanks to Tonnel party № 6 of Mosmetrostroy and Mechanization Directorate of Mosmetrostroy everything went without a hitch.

The time of Alma-Atinskaya station commissioning is drawing on. It is projected on December, 2012. Mosmetrostroy staff performs the following works on the site round-the-clock: finishing, construction of halls, street exits, laying of rails and electric installation works.