OREANDA-NEWS. LLC "STROYGAZMONTAZH" started to execute the works at Kubanskaya compressor station within the construction project "Russia – Turkey gas pipeline capacity expansion at Izobilnoe – Dzhubga part for gas supply provision to Dzhubga – Lazarevskoye – Sochi gas pipeline".

The customer is CJSC "Gazprom invest Yug", the General Designer is OSC "Giprospetsgaz" and the Operating Company will be LLC "Gazprom transgaz Krasnodar".

The works within Kubanskaya CS for temporary buildings and facilities development (main construction office, contractor’s operation base, accommodation facilities) have been completed, foundation laying works for compressor station facilities come to an end, works for process equipment installation (4 GPUs of 12 MW each with aggregate capacity of 48 MW) are in process.