OREANDA-NEWS. Highland Gold Mining Limited ("Highland Gold" or the "Company") is pleased to announce that conveyance, screening and milling construction works at its new stand-alone processing facility at Belaya Gora have been concluded successfully. The Company has initiated the commissioning of these major plant component installations and will thereafter proceed with the verification of the operational readiness of the full process flow scheme followed by wet testing and first ore feed. Initial gold bullion is expected to be delivered in May. After the Novoshirokinskoye polymetallic mine, Belaya Gora is the Company's second major stand-alone process facility construction.