OREANDA-NEWS. This week gas turbine was completely delivered to the construction site of Zhodinskaya TPP. All the necessary auxiliary equipment was also delivered with the main set of Gas Turbine, which was shipped from Norrkoping (Sweden) by E4 Group. The supplier of the main equipment is Siemens Industrial Turbomachinery AB.

As of today, pile driving and trimming works are fully complete. Works related to site cleaning-up, drawing-up of as-built documentation and handing over of the remaining pile fields for foundation are ongoing. Boiler is being delivered. In late April, it is planned to start delivery of the steam turbine.

It is to remind that a new 65MW CCPP is being constructed upon the order of Republican Unitary Enterprise "Minskenergo" under the state energy efficiency and energy saving program of the Republic of Belarus. E4 Group acts as an EPC-contractor.