OREANDA-NEWS. Works commissioned to the Titan-2 employees for 2013 are on completion stage on the site of the construction of the water-water nuclear reactor complex in “St Petersburg Nuclear Physics Institute named after B.P. Konstantinov and Kurchatov University Research center (Gatchina). Their acceptance is carried out through working subcommittees.

The complex of works is carried out on the following objects:

• Building 104, a neuron research building with a technical block. ZAO “TITANVENTEH” and OAO “Sosnovoborelectromontazh” have completed on ventilation and lighting set up.

• Building 105, a multimachine automated complex (an office building for scientists). ZAO “TITANVENTEH” has completed the air pressure test of the heating system.

• Building 116 Reserve diesel power station block (RDPS). RDES works are completed by OAO “Montazhno-stroitelnoye upravlenie №90”. Works on administration relay cabinets and other electric -technical systems are done by OAO “Sosnovoborelektromontazh”, and the electric-technical systems adjustment is finished up by ZAO “TITANENERGONALADKA”.

• Building 122 Liquid radioactive waste repository. Mechanic and installation works are completed by OAO “Montazhno-Stroitelnoye Upravlenie №90”.

• Building 103, Cooling tower. Works are completed by “Montazhno-Stroitelnoye Upravlenie №90”, pipeline installation, and accomplishment - by OAO “Upravlenie avtomobilnogo transporta.”