OREANDA-NEWS. As a result of the bid evaluation the proposal of LLC "STROYGAZMONTAZH" for the construction of gas trunkline for Izobilny - Nevinnomyssk CS (the Stavropol Territory) was announced to be the best one among OAO Gazprom proposals.

The Customer of the gas pipeline is OOO Gazprom transgaz Stavropol.

LLC "STROYGAZMONTAZH" will construct two start-up complexes of 98.6 km in total, namely: km 43.4 - 98.6 and km 0. - 43. Builders have been already involved in the project execution. The commissioning of the first start-up complex is scheduled for May 2014. The construction of the second start-up complex will last till September 2014.

Four crossings (3.1 km in total) will be constructed by horizontal directional drilling under the corridors of flow lines, utilities and rivers. The total scope of construction and installation works will be performed, including off-load and on-load start-up activities.