OREANDA-NEWS. Concrete placing in a 163 meter long platform section has been completed at Tagansko-Krasnopresnenskaya subway line Kotelniki station which is under construction.

Erection of the support columns and concreting of the upper floor over the platform section are nearing completion. The concreting operations at the station are about 80% complete. The concreting operations are to be completed by the beginning of March.

Technical premises and ticketing areas will be put in place in the station entrance hall where the walls are being erected. They are placing rebar cages and conduct preparations for concreting the technical premises in the first level areas (platform section).

Wall concreting and technical premises building operations are also underway in the turnaround siding areas.