OREANDA-NEWS. During the period of 1-30 May 2014 construction works in Sonyachna Brama residential complex were carried out according to the schedule.

In the residential building B-12, installation of elevators equipment and apartments entrance doors is at the final stage. Installation of radiators and final finishing works in public areas are currently underway.

In the residential building B-13, final finishing works are 95% complete with floor underlayment works in apartments being 70% finished. In the residential building B-14, roofing works are at the final stage.

Completion of the third phase of Sonyachna Brama residential complex is scheduled for the end of second quarter of 2014.