OREANDA-NEWS.  Calvalley Petroleum Inc. provides the following operations update for shareholders. The Company is pleased to announce that production operations at Block 9 are being resumed as storage capacity at the central processing unit (CPF) becomes available.

The Company has been informed by the operator of Block 18 that the oil pipeline between Block 18 and the Ras Isa Terminal on the Red Sea has been repaired. Trucking of crude oil to Block 18 was reinstated effective May 31, 2014.

Truck shipments were suspended by the operator of Block 18 on May 14, 2014. During the period May 15, 2014 to May 31, 2014 the Company produced approximately 14,000 barrels of crude oil. The Company will be resuming production operations at Hiswah, Ras Nowmah and Ras Nowmah South as soon as storage capacity is made available.