OREANDA-NEWS. August 15, 2014. E.ON Russia JSC intends to exercise the right of pre-schedule commencement of performing its obligation on capacity supply at Facility No. 3 of Berezovskaya GRES, whereof it has notified Center of Financial Settlements today.

The new date of commissioning Power Unit No. 3 of Berezovskaya GRES is June 1, 2015, which is five months earlier than the declared date.

This rescheduling is due to reduction of the facility construction period as a result of the project optimization performed at the beginning of the current year.