OREANDA-NEWS. JSC "Lengazspetsstroy", which is a part of SGM Group of Companies, completed the performance of tests on the GP1 - km 0 and 0 km - 57 km of Bovanenkovo - Ukhta trunk gas pipeline. The total length of tested sections is 86.6 km.

In the nearest time the drying and nitriding of a pipeline for conservation of ready assembled sections are be done. A tie-in in the operating gas pipeline is be performed by the December of this year. At present time JSC "Lengazspetsstroy" carries out remediation work, construction of onshore facilities and land improvement.

ZAO Yamalgazinvest is the Customer of the works being conducted on linear portion of gas pipeline. LLC "STROYGAZMONTAZH" is the General Contractor. The construction and installation works are planned to be performed on the section of the second string, entrusted to JSC "Lengazspetsstroy" and to be completed by the end of 2014 or at the beginning of 2015.

As of today the total length of gas pipeline, which JSC "Lengazspetsstroy" is to build in the framework of 2nd string of Bovanenkovo - Ukhta, totals over 193 km.