OREANDA-NEWS. Stage one of the construction project at Georgievsk compressor station has been completed, the construction site now powered with electricity and fed with gas.

Georgievsk CS-8 is a part of the construction project for "Reconstruction of the compressor stations at Privolnoye - Mozdok section of the North Caucasus ‒ Center system of trunk gas pipelines".

The customer of the construction project is LLC "Gazprom Tsentrremont".

LLC "STROYGAZMONTAZH" has finished stage one of the construction project including installation of two gas pumping units (GPA-10PM) with a capacity of 10 MW manufactured by JSC "UEC - Gas Turbines", construction of basic infrastructure group of buildings. It is expected that next year installed will be two more gas pumping units of similar capacity.

The total amount of gas distribution units to be installed at Georgievsk compressor station is six, their aggregate capacity being 60 MW. So the capacity of the station itself will be nearly doubled.