OREANDA-NEWS.The main document for power engineers the Certificate, which confirms the readiness of company to provide reliable power supply to customers during peak loads was awarded to Lipetsk power engineers, the company's press service reported.

Certificate 3 was awarded by Dmitry Pankov, Head of Cooperation between JSC "IDGC of the Center" and Market Entity Department.Alexander Kornilov, Technical Director of JSC "Lipteskenergo", Dmitry Butuzov, Chief Inspector of Technical Inspection  department of JSC "IDGC of the Center", Vasily Schedrin, Deputy Technical Director for Operative and Technological Management and executives of production departments presented at the awarding ceremony. The document, which confirms the successful preparation to the peak loads period, is signed by Evgeny Makarov, General Director of JSC "IDGC of the Center".

Dmitry Pankov, said that JSC "Lipetskenergo" was among the first companies which received the Operability Certificate, it shows the company stability and reliability.

"The special committee inspected the condition of the company production departments for the last nine months, and signed act, on which basis the Certificate was issued", - said Dmitry Pankov. All structural departments of JSC "Lipetskenergo" received preliminary documents certifying the technical readiness to operate during autumn and winter peak loads.