OREANDA-NEWS. January 28, 2008.  Almost 1 thousand km of new transmission lines were constructed in the region, additional capacities will equal 402 МWA

Results of realisation of investment programs of 2007 are summed up. On the tentative estimations, expected realisation of the plan of capital investments will be 3 108 626 thousand rubles, or 102 % of the planned volumes.  

Komienergo works most effectively in this direction. The company pursued the scheme of 104 % input of a fixed capita, investments into development of a network complex of the Republic of Komi equaled 568 436 thousand rubles last year.

According to the results of 2007 Vologdaenergo put fixed capital equal to 520 500 thousand rubles (102 %), Karelenergo - to 349 100 thousand rubles (101 %), Kolenergo - to 299875 thousand rubles, or 101 %.

Practically 10-time larger amount of transmission lines was put into operation in Kolenergo in comparison with planned targets of 2007. Actually in DGC the length of the networks increased by 88.9 km though; it was originally planned to enter only 7.76 km. 

In Komienergo length of the new transmission lines, which were constructed and reconstructed within the limits of the investment program equaled 166 km (116.7 %) In the Karelian distributive network company the length of TL increased almost by 100 km that makes 109.5 % of realisation of planned targets.

As a whole on companies of IDGC of the North-West, 402 МWA capacities were put in addition. The basic forces and means of Vologda power men were directed to increasing capacity last year and according to the results of the year, they fixed input of 66 МWA of additional capacity at the plan 43.3 МWA (152.3 %). It is the most essential volume of input of additional capacities in the whole Northwest region.

With overfulfillment plan (104.1 %) on this parameter Komienergo worked – 87.13 МWА. They executed their obligations for 100% on capital assets (km/MWA); and in Pskovenergo.