OREANDA-NEWS. February 1, 2008. The development of all directions of economy, including electro-power sphere, escalating of power, realization of process of updating of power supplying systems and distributive networks is one of priority directions of carried out policy of the head of state.

The civil-engineering project of 220-KVt substation "Salyan" is one of priority actions, carried out in this direction.

Informing on it, the press-service of joint-stock company " Azerenerji " marks, that two transformers are already established at substations by capacity of 125 MVA each of them. And at office building and trunks 10-KVt closed distributive power object civil and erection works are completed. Now the work on lining of road in direction of substation is carried out.

At 110 and 220-KVt open distributive power objects works on planning of the territory, on setting of bases of equipment which are subject to installation are executed. Now cable channels are stacked.
Within the framework of project reconstruction works by accelerated rates are conducted at other substations too.
Let's note, that at 220-KVt substation "Masalli" are completed works on planning of territory and excavations. Now here is carried out the setting of 5 bases.

Simultaneously, works on protection of territory in which will soon begin constructions at 330-KVt substation "Imishli" equivalent open distributive power object proceed. At the territory of base of electric equipment, portals are established and are mounted more than 150 metal constructions, more than 20 base blocks were also established and some portals were replaced.

The base of 4 units of portals is established at 220-KVt open distributive power object at 330/220/110-KVt substation "Ali-Bairamli", and base blocks are established at 330-KVt open distributive power object, are mounted more than 60 metal constructions. Now works are conducted in conformity to the planned schedule.

Let's remind, that within the framework of civil-engineering project PSL/PS "Parsabad-Astara" construction of high-voltage PSL by extent of 350 km. and reconstruction of substations "Imishli", "Ali-Bairamli" and "Masalli" is stipulated.