OREANDA-NEWS. December 17, 2008. After visiting the site, Akbulatov heard the report of the director of Atomstroy Investment Construction Concern Artyom Butov, who said that the launch of the first start-up complex of the plant was scheduled for Sept 2009. “Simultaneously, we will start testing the boilers of the second launching complex,” Butov said.

Next year the project will receive almost \\\\$100mln. The American party is financing the project without delays. For the moment, the 1st and 2nd boilers are 90% ready. The heating main is also ready for service.  
After inspecting the construction site and examining the relevant reports Akbulatov said that the project complied with the schedules and enjoyed stable financing.

He said that in the winter 2009–2010 the plant would already be operative. “We must not launch the plant without haste so as to avoid problems in the future,” Akbulatov said. He pointed out the high efficiency and professionalism of the Krasnoyarsk branch of Atomstroy.