OREANDA-NEWS. July 28, 2009. All main plants and production units of KAMAZ started executing the company’s July order.

This month the mother gathering conveyors of the automobile plant will work to 28 July inclusive – without interruption four days a week. By order of Director General of KAMAZ Inc. a working schedule of units and productions of the whole production chain as well as services not engaged in execution of the primary process was determined.

In July 2595 vehicle sets will be gathered at the automobile plant, the finishing production of KAMAZ. This month a part of finished products will also be delivered to Trade and Finance Company and Foreign-Trade Company of KAMAZ and shipped to customers. A part, like a 400 vehicles order for Yemen, for instance, will be delivered in August.

2939 engines will be produced at KAMAZ-Diesel. In July the workers of KAMAZ-Diesel will have to deliver 3090 engines and power units in all to the mother gathering conveyor of the automobile plant and to the customers of the enterprise itself.