OREANDA-NEWS. April 08, 2010. The investment program for 2010 was approved at the meeting of the Board of Directors of IDGC of Centre held in presentia. The volume of capital investments was planned at the level of 10,7 bln Rubles, including 5,6 bln Rubles will be spent for technical re-equipping and reconstruction, 5,1 bln Rubles – for new construction and extension. The investment program is planned to be financed by 28% (3 bln Rubles) by means of borrowed funds.

In 2010 it is intended to introduce 875 MVA of transformer capacity and 3 209 km of power transmission lines.

Technical re-equipping of the substation (SS) of 110/6 kv “No. 10” (Voronezhenergo), reconstruction of the second priority of SS-110/6 kv “Sovetskaya” (Bryanskenergo), proceeding of construction of SS-110/10 kv “Rodniki” (Kurskenergo) and SS-110/10 “Manezhnaya” (Lipetskenergo), reconstruction of substation of 110/10/6 kv “Zapadnaya” (Orelenergo), completion of construction of SS-110/6/6 kv “Kotorosl” (Yarenergo) will be the largest investment projects of IDGC of Centre in 2010.