OREANDA-NEWS. February 22, 2011. Deputy director for capital construction of the branch of IDGC North-West Komienergo Dmitry Vylegzhanin have inspected the course of operations.

Reconstruction of line 110 kV "Mikun - Edva" on the site Vozhskaya – Edva is ready for 45%. The head of the Department of Capital Construction of IDGC North West Lydia Nikandrova and deputy director for capital construction of the branch of IDGC North-West Komienergo Dmitry Vylegzhanin have inspected the course of operations. They noted the good work of the contractor.

Major reconstruction work is planned to complete before the end of March. By this time at the line will be replaced 147 wooden poles  for  129 steel multi-faceted with a lifetime of more than 60 years - their physical properties make it possible to increase the distance between the poles and reduce the number of poles on the line.

Also among up-to-date technologies - a new type of ground wire, polymeric insulators and multifrequency vibration suppressors. All this will improve the reliability and quality of power supply of  Ust-Vymskiy and Udorskiy areas with a population of more than 40 thousand people. Investments in the implementation of the next phase of the project amount to 84 million rubles.
Total amount of investments in the project from 2007 to 2011 will exceed 260 million rubles.