OREANDA-NEWS. March 03, 2011. Branch of JSC "IDGC North-West" “Vologdaenergo”  put into operation the overhead transmission line 10 kV Ust-Alekseevo – Yakutino  after reconstruction. During the implementing of the investment project on the transmission line (12 km) were installed new wooden poles (impregnated), mounted self-supporting insulated conductor.

Power line "Ust-Alekseevo – Yakutino” is located in Veliky Ustug’s  area. It provides electricity for consumers of villages Yakutino and  Ust-Alekseevskoe, as well as for a number of socially significant facilities and  TV station.

After reconstruction of the transmission line the reliability of electricity supply will be significantly improved.  Also, there will be new opportunities and prospects for development of infrastructure of  Velikiy area. Cost for investment projects amounted to 13.9 million rubles.