OREANDA-NEWS. July 13, 2011. From 00-00 July 11 to 00-00 July 22, in accordance with the schedule approved of by the Department of Municipal Services under Administration of Krasnoyarsk City CHP-1 will be performing scheduled repair works involving hot water supply interruption.

During the period referred to one will undertake repair and replacement of valves and tubes of Boiler Units No. 1-9 relying on the findings of hydraulic tests performed in May 2011 during hot water supply interruption. Additionally, one will perform control and calibration of flow metering devices. As per the technology, such repair works necessitate shutdown of the plant primary equipment and hot water supply interruption.

In this connection, during the scheduled repair works performance period, supply of hot water to consumers within the Kirovsky, Leninsky and (partly, to Zatonskaya Street) Sverdlovsky Districts of Krasnoyarsk will be discontinued.

Hot water supply interruption is a necessary measure. Notably, the works are mostly proceeding during the non-heating season without hot water supply limitation. Thus, currently in progress at CHP-1 are works for replacement of the delivery water reheaters tubing system, repair of main-line pumps, Boiler Unit No 9 delivery water tubes. However, some works do require hot water supply interruption.

To ensure optimization of hot water supply interruption terms specialists of Krasnoyarsk Heating Network branch (parallel to works at Krasnoyarsk CHP-1) will perform repair works on the shut-off heating network sections.

On the night of July 21/22 works for resumption of consumer hot water supply will commence.