OREANDA-NEWS. April 13, 2012. OJSC SK MOST Group of Companies carries on with construction of a viaduct over Shiroky Log at the 1418th kilometer mark of Agryz – Druzhinino section, Gorky Railway Line).

The bridge builders are using GPK 130U Crane to install seven span decks out of fourteen. Work continues on pillar footings, grillage and pillar concreting. Hunnebeck slipform (Germany) is used to erect the viaduct pillars. The builders have completed the Bridge Crew Building, Bridge Lineman Station; they completed facilities of fire water pools and cesspools and installed a security fence, and they are now erecting a Security Guard Building.

According to the work schedule, the viaduct will be put in service in November 2012.